Permit Turnaround Information

Average Review Times

Average review times are based on working days from Applied Date through Approved Date.  This average does not take into account the days the applicant took to respond to corrections.

  1. BUILDING
  2. CIVIL

AVERAGE REVIEW TIMES*

TYPE 2023 
(1st Quarter)
2022 2021 2020 2019
RESIDENTIAL          
Adult Family Homes 15 18 15 10 9
Additions 24 9 18 18 10
Accessory Dwelling Units (ADU) 18 40 40 25 12
New Residential 34 42 48 19 16
Duplex 0 105 9 17 98
Accessory Buildings  15 19 27 40 12
Tenant Improvement (T.I.) / Remodel 8 9 12 12 7
Apartments (Units) 0 90 60 44 94
Townhomes (Units) 90 102 0 96 0
Mobile / Manufactured Homes 5 7 17 13 16
COMMERCIAL          
New Commercial 35 37 35 50 84
Additions 0 9 7 0 20
Tenant Improvement (T.I.) / Remodel 18 26 25 20 14
Cell Tower 19 14 13 49 9
Plumbing / Mechanical 11 8 12 18 11
OTHER          
Signs 16 28 12 19 16
Solar Permits 12 8 7 8 6
Fire Permits 22 15 13 17 21
Electrical Permits 8 9 5 5 3
Demolition Permits 5 7 5 6 7
Business Licenses 35 27 25 30 31

Target Permit Review Times

  1. BUILDING
  2. CIVIL
  3. LAND USE

Target Review Times

COMMERCIAL  
New Commercial 4 - 6 Weeks
Tenant Improvement (T.I.) 3 - 4 Weeks
Mechanical 2 - 5 Weeks
Plumbing 2 - 5 Weeks
Electrical 2 - 5 Weeks
Re-Roof 1 - 5 Weeks
SIGNAGE / SOLAR PANELS  
All Signs 2 - 5 Weeks
Solar PV Systems 3 Weeks
RESIDENTIAL  
New Residential 3 - 6 Weeks
Basic Residential 2 - 5 Weeks
Addition / T.I. 2 - 5 Weeks
Mechanical / Plumbing / Re-Roof 2 - 5  Days (over counter/online)
Adult Family Homes 2 - 5 Weeks
Accessory Dwelling Units (ADU) 2 - 5 Weeks