Roadwork and Maintenance closures

CITY OF MARYSVILLE PROJECTS:

2020 Pavement Preservation Program

During the month of July and August, the city’s contractor, Reese Construction Company, will be milling, paving and restriping sections of:

  • 67th PL NE between 67th Ave NE & 71st Ave NE as well as side streets
  • 67th St NE between 71st Ave NE & 76th Dr NE as well as side streets
  • Grove St between 67th St NE & 83rd Ave NE.

As part of these activities, the city’s contractor will be upgrading curb ramps to meet current ADA requirements. After paving work is completed, temporary channelization/striping will be in place for a minimum of 14 days before permanent channelization/striping can be installed. Paving work has been completed at 44th St NE between 67th Ave NE & 83rd Ave NE. Currently, the contractor is working on raising utility structures and paving driveway aprons. Permanent channelization/striping is scheduled for the end of July.

Civic Center Project

Delta Ave between 5th St & 8th St is subject to intermittent one way traffic control and steel sheet in the roadway due to utility installation. 

State Avenue Widening Project - 100th to 104th Streets

Drivers can expect occasional alternating one-way traffic closures as underground utilities are being installed as the project evolves. Traffic will be able to get through in both directions.

Another full road closure on State Avenue at the Quilceda Creek crossing (just north of 100th St) is anticipated near the end of July or the first of August.  Advance notice will be given. The duration of this closure will be fairly limited, lasting only 2-3 days over the course of a weekend. The purpose of the closure is to allow sufficient room to set up a large crane to place bridge girders.  

The city’s contractor for this project is Strider Construction.

When this phase is complete next year, the State Avenue roadway between 100th Street NE and 104th Place NE will have five lanes instead of three along with curb, gutter and sidewalk and street lighting to improve traffic and pedestrian safety. Construction of the last remaining corridor from 104th Pl NE to 116th St NE is not yet funded.

1st Street Bypass

Scarsella Bros. will demolish and rebuild the NW corner of 1st Street and State Ave. During this time, pedestrians will be escorted around the work area due to the heavy construction activity. ROAD CLOSURES: Monday, July 6th to Friday, July 10th - One north bound and one south bound lane will be closed on State Ave., and 1st Street will be closed from State to Alder for pavement work. Columbia Ave. will be closed. Public Works access will be at Alder Ave. during this time. Detour signs will be in place.

Additional work in the intersection will follow to install new stamped concrete crosswalks at this location. We appreciate your patience and understanding as this work is performed for completion of the project sometime in August.

City council awarded the 1st Street Bypass construction contract on Monday, May 13, 2019 to Scarsella Bros., Inc., in the amount of $12,947,526.86. From Kent, WA, Scarsella is well qualified to build the new arterial, having built many similar projects.

The bypass project includes widening 1st Street from (2) lanes to (5) lanes, between State and Alder, and will extend 1st Street as a (2) lane bypass from Alder to 47th Avenue. The roadway improvements will include a shared-use path, illumination and traffic signal improvements. With completion of WSDOT’s interchange project at SR 529 in 2022, the bypass will provide important commuter access to I-5, and allow them to bypass congestion on 4th Street and the BNSF crossing. 

Due to construction on 47th Ave NE, commuters and residents are advised to avoid 47th Ave NE, south of 3rd Street at this time. The roadway is still open to 2-way traffic with one narrow lane in each direction. If use of 47th Ave cannot be avoided, please Give’m a Brake and move cautiously through the construction area. 

We appreciate your patience during this important project. We will do our best to minimize impacts to the community, and to build the City an exciting new roadway project. Please contact Steven Miller, Senior Project Manager at 360.363.8285 or smiller@marysvillewa.gov with any questions or concerns.

Street Department

Crews will begin crack sealing on Ingraham Blvd as well as 100th St. Drivers will experience intermittent lane closures, flaggers will be on the roadway. Work is weather dependent.

WSDOT Projects:

108th St NE Intersection Improvements - #9195

Highway: SR 9 Region: Northwest County: Snohomish Location: Milepost(s) 21.77 - 22.03
Contact: Mark Sawyer, Project Engineer, 425-225-8799
Description: WSDOT contractor crews are building a single-lane roundabout at the intersection of SR 9 and 108th Street Northeast in Marysville.
Project webpage
Work Scheduled:  

  • SR 9 CLOSURE: 8 p.m. Thursday, July 9 to 5 a.m. Monday, July 13 The intersection of SR 9 at 108th Street Northeast will be closed. A signed detour will be in place at 84th St NE and 172nd St. Emergency services will be allowed through the closure and local access for residents is permitted. 
  • Tuesday, July 14, to the morning of Friday, July 17 - A single lane of SR 9 will close between 84th Street Northeast and 108th Street Northeast from 9 p.m. to 5 a.m. nightly.
  • Sunday, July 19, to the morning of Friday, July 24 - A single lane of SR 9 will close between 84th Street Northeast and 108th Street Northeast from 9 p.m. to 5 a.m. nightly.

Snohomish County Projects

No information at this time.

Private Contractors Projects

No information at this time.

Last updated July 9, 2020